Mar. 09, 2012

The Project Manager has already wrapped up his visit in Nigeria, actually mainly in Lagos and Abuja in the last two weeks.

Nov. 04, 2011

Last week it's been a hot week on KOMO site, which has pushed the overoofing work of the last senior blocks. Our builders on site are building two single-level Senior Blocks with overroofs, one is  7 units a row in two...

Sep. 13, 2011

By far there have been nearly 500 ARK units used for EXXON'S PNG LNG Project on KOMO site.The single level 84-unit Office Area has been being trimmed out in last two weeks with the huge over roofs on. Even though there were...

Aug. 23, 2011

Last week, all the office units have been put onto the foundations in the Office Area; and our builders on site have finished the rubber gaskets in-between all the units and tightening the connection bolts. Part of the internal...

Jul. 06, 2011

EPC5B——KOMO Airfield Accommodations Facilities Project within The PNG LNG Project, in which ARK is on, has two camps to build, one of which called Pioneer Camp has already been finished last November.In the Pioneer, we have built...